Empennage (June 2003 - December 2004)

The Empennage is what most people would call the tail. This is the first major assembly, and everyone has to build one, whether they are building a "quick build" or a "slow build" kit.

Total time worked on the Empennage: 215 hours

Horizontal Stabilizer
2003-06-26   0.0   -  Empennage kit arrives.
2003-06-27   2.0   -  Inventory.
2003-07-09   2.5   -  Rear Horizontal Spar Assembly.
2003-07-11   3.0   -  HS-411 Assembly.
2003-07-12   5.0   -  Began work on the Front Spar Assembly.
2003-07-13   0.0   -  Created a website.
2003-07-19   7.0   -  Finish Front Spar Assembly.
2003-07-20   4.0   -  Assemble Left Horizontal Stabilizer.
2003-07-24   3.0   -  Assemble Right Horizontal Stabilizer.
2003-07-25   2.5   -  Preparing the HS parts for assembly - part 1.
2003-07-26   7.0   -  Preparing the HS parts for assembly - part 2.
2003-07-27   3.5   -  Preparing the HS parts for assembly - part 3.
2003-07-29   5.0   -  Riveting the Horizontal Stabilizer - part 1.
2003-08-02   5.0   -  Riveting the Horizontal Stabilizer.
2003-08-03   3.0   -  Riveting the Horizontal Stabilizer.
2003-08-05   2.0   -  Discovered major screw-up.
2003-08-06   1.5   -  Fixed major screw-up.
2003-08-08   2.5   -  Riveted Left skin to Front HS spar.
2003-08-09   2.5   -  Riveted Right skin to Front HS spar.
2003-08-10   6.0   -  Horizontal Stabilizer done!
  67    hours

Vertical Stabilizer
2003-08-12   4.0   -  Started Vertical Stabilizer.
2003-08-14   2.5   -  More Alodining.
2003-08-16   5.0   -  More deburring.
2003-08-17   4.5   -  Finally some rivets.
2003-08-18   1.5   -  Deburr the skin then rivet the outside ribs.
2003-08-19   2.5   -  VS complete!
  20    hours

Rudder
2003-08-23   27.0   -  Started on the Rudder.
2003-09-02   14.5   -  Rudder almost done.
2003-09-08   2.5   -  Rudder is done - except for fiberglass tips.
  44    hours

Elevator
2003-09-11   24.5   -  Work on elevators.
2003-09-23   14.5   -  Finished the right elevator
2003-10-03   23.0   -  Finished the Left Elevator.
  62    hours

Fiberglass
2003-10-18   4.0   -  Work on Right Elevator Fiberglass Tip
2003-11-11   3.0   -  Fix Screw-up, Paint Fiberglass Tips.
  7    hours

Paint
2003-11-02   2.0   -  Painted the Right Elevator Fiberglass Tip.
2004-12-04   2.0   -  Come in out of the rain.
2004-12-11   4.0   -  Prep and prime the HS.
2004-12-18   2.0   -  Painting the HS.
2004-12-20   1.0   -  Painting the HS.
2004-12-22   4.0   -  Painting the HS.
  15    hours