Project Statistics (June 2003 - April 2009)

This page shows project statistics, including the hours worked and the number of rivets set for each major component.

Total hours worked  1501.5
Total rivets set   9110

                     Hr /     Hr /     Hr /     Hr /     Days /   
 Year   
 Months   
 Days   
 Hours   
 Year   
 Month   
 Week   
 Day   
 Week   
 2003  7  57  276  276  39.4  9.9  4.8  2
 2004  12  145  473.5  474  39.5  9.9  3.3  3
 2005  12  96  360  360  30  7.5  3.8  2
 2006  11  81  338  338  30.7  7.7  4.2  1.8
 2007  5  12  28.5  29  5.7  1.4  2.4  0.6
 2008  5  7  24.5  25  4.9  1.2  3.5  0.4
 2009  1  1  1  1  1  0.3  1  0.3

 4.4

 53

 399

 1501.5

 340

 28.3

 7.1

 3.8

 1.9

 

Empennage
hours  
  rivets  
Horizontal Stabilizer.  67     580   
Vertical Stabilizer.  20     294   
Rudder.  44     582   
Elevator.  62     754   
Fiberglass.  7     0   
Paint.  15     0   

 

  215  

  2210  
 
Wing
hours  
  rivets  
Spars.  48     434   
Ribs.  68     0   
Left Wing.  64     1563   
Left Fuel Tank.  79.5     617   
Left Flaps and Ailerons.  62     547   
Right Wing.  54.5     1563   
Right Fuel Tank.  59.5     617   
Right Flaps and ailerons.  39.5     547   
Fiberglass.  22     102   
Fixtures and stands.  32     0   
Paint.  0     0   

 

  529  

  5990  
 
Fuselage
hours  
  rivets  
Bulkheads.  121     514   
AFT Section.  47     396   
Center Section.  79.5     0   
Forward Section.  171     0   
Fixtures and stands.  4.5     0   
Top.  35.5     0   
Cabin.  192     0   

 

  650.5  

  910  
 
Firewall Forward
hours  
  rivets  
Cooling System.  5     0   
Engine.  73.5     0   
Engine Test Stand.  12     0   

 

  90.5  

  0  
 
Interior
hours  
  rivets  
Seat cushions and backs.  16.5     0   
Side panels and other surfaces.  0     0   

 

  16.5  

  0